Noida International Airport (YIAPL): 14.36 MW Solar, Piling & Fencing
Pile foundations and chain-link perimeter fencing for the 14.36 MW solar power project of YIAPL, the company building Noida International Airport in Uttar Pradesh.
About the YIAPL, Uttar Pradesh project
In 2025 Tata Power Renewable Energy engaged Arrays Ingenieria for the construction of pile foundations (300 mm diameter, 1.8 m to 2.3 m deep) and for the supply, civil work and erection of chain-link fencing, with a tentative fence length of about 6.25 km, at the 14.36 MW YIAPL solar power project.
A plant of this size needs its foundations in and its perimeter secured before installation crews can move in.
Our scope of work
- Pile foundations, 300 mm diameter, 1.8 m to 2.3 m deep
- Supply, civil work and erection of chain-link fencing (about 6.25 km tentative length)
- All manpower, machinery and material for the fencing
Photos

How the Project Unfolded
The work, stage by stage, as it was ordered and delivered.
Pile foundations
Construction of pile foundations, 300 mm diameter, 1.8 m, 2 m and 2.3 m deep.
Chain-link fencing
Supply, civil work and erection of chain-link fencing, tentative length about 6.25 km.
Challenges and How We Handled Them
An airport site
Work at Noida International Airport runs under strict access and safety control, with every crew and vehicle accounted for.
Kilometres of fence
Around 6.25 km of chain-link fencing means steady, surveyed progress: posts set in concrete, mesh tensioned, gates aligned.
Piles to suit the ground
Three pile depths were used, matched to the ground conditions across the 14.36 MW site.