- Installation runs in a fixed order: civil works, structures, modules, DC cabling, inverters, AC side, earthing and protection
- Every connection is a potential fault: torque, crimping, gland sealing and labelling matter
- Commissioning proves the plant: insulation resistance, polarity, string voltages and currents, earth resistance, protection and grid tests
- Inspection and approvals (DISCOM, CEIG) come before energisation
- At handover you should receive as-built drawings, test reports, warranties, approvals and an O&M manual
Before anyone picks up a tool
- Approved layout and single-line diagram; structure and foundation design
- Safety plan, permits and inductions for every worker; the client's site rules signed off
- Material receipt checks: module and inverter models, serial numbers and certificates matched to the specification
- A storage area that keeps modules flat, dry and secure
Stage by stage: installation
- Civil worksEarth-pit chambers and covers, equipment foundations for inverters, ACDB and ITB, cable trenches, and for ground-mount plants the piles or foundations, drainage and fencing.
- Module mounting structuresErect and align the structures to the design tilt and levels; torque every bolt; on sheet roofs, fix to purlins with the right clamps and seal every penetration.
- Module installationMount modules with the specified clamps and torque; keep gaps for expansion; do not stand on modules.
- DC cabling and stringingConnect module to module and run string cables in UV-protected conduit or trays to the combiner boxes or inverters; crimp MC4 connectors with the right tool; label every string.
- InvertersMount inverters on their stands or foundations with ventilation clearance; terminate DC and AC cables; configure grid settings.
- AC sideLay armoured AC cables to the ACDB and the point of connection; terminate with proper glands and lugs.
- Earthing and protectionSeparate DC and AC earthing with tested earth pits; lightning arrestors; surge protection devices; equipotential bonding of structures.
- AncillariesModule cleaning system, walkways or lifelines, safety signage, fire extinguishers and monitoring.

Commissioning: the tests that prove the plant
| Test | What it checks | Typical acceptance |
|---|---|---|
| Visual inspection | Damage, mounting, cable routing, labels, clearances | No defects; matches drawings |
| Polarity and continuity | Every string wired correctly | Correct polarity on every string |
| String open-circuit voltage (Voc) | Correct number of modules and no faulty ones | Within a few per cent of expected for the conditions |
| String short-circuit or operating current | Strings performing alike | Strings matched within tolerance for the irradiance |
| Insulation resistance | No leakage from DC conductors to earth | Above the minimum for the system voltage |
| Earth resistance | Earthing system effective | Within the design value |
| Inverter functional tests | Start-up, grid synchronisation, anti-islanding and protection settings | Operates and trips as specified |
| Performance check | Output against irradiance | Consistent with the design yield |
Tests are recorded on formats that follow IEC 62446-1 and the DISCOM's and Electrical Inspector's requirements, so the same records serve the client, the approvals and future O&M.
Inspection, approvals and going live
- DISCOM inspection and, where required, the Electrical Inspector's (CEIG) inspection
- Installation of the bidirectional or generation meter
- Synchronisation with the grid and, at tea estates and factories with diesel back-up, with the DG sets
- Commissioning certificate and, for scheme projects, portal updates
What you should receive at handover
- As-built layout and single-line diagram
- Test reports for every string and every test above
- Equipment list with serial numbers, warranty certificates and BIS / ALMM documents
- Approvals: DISCOM, net-metering or open-access, CEIG
- O&M manual, cleaning procedure and a contact for faults
- Training for the site electrician or estate team
On many of our projects the installation & commissioning scope also includes collecting the warranty certificates and the client's I&C-cum-handover certificate, so the plant owner and the EPC both close the project with a complete file.
Need an installation & commissioning partner for a rooftop or ground-mount plant? Our veteran-led crews work Pan-India.
Get a free solar quoteFrequently asked questions
What does installation and commissioning (I&C) of a solar plant include?
How long does it take to install a 1 MW solar plant?
What tests are done when a solar plant is commissioned?
What documents should I get after solar installation?
Sources
- PIB: MNRE notifies the revised Quality Control Order for solar photovoltaic products
- Mercom India: Net metering approved for rooftop solar up to 500 kW
This guide explains public policy in plain language for planning purposes. Rules, rates and deadlines change: confirm the current position with the notifying authority, your DISCOM and your tax adviser before you commit. Last checked 11 Oct 2026.